| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Culvert Removal and Disposal | 1 | each | $10,000.00 | $10,000.00 | Construction |
| New Large Culvert (Supply and Installation) | 1 | each | $80,000.00 | $80,000.00 | Construction |
| Site Preparation and Excavation | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Backfilling and Compaction | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Roadway Reconstruction and Paving | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Erosion Control Measures | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Traffic Control and Safety Measures | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Estimated Bid Value | $150,000.00 | ||||