| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Two-lane overpass construction (substructure, girder placement, superstructure) | 1 | lot | $8,000,000.00 | $8,000,000.00 | Construction |
| Bridge approach slabs installation | 2 | each | $150,000.00 | $300,000.00 | Construction |
| Guardrail installation | 1000 | linear foot | $50.00 | $50,000.00 | Construction |
| Guardrail transitions installation | 4 | each | $5,000.00 | $20,000.00 | Construction |
| Bridge sign brackets installation | 4 | each | $1,500.00 | $6,000.00 | Construction |
| Bridge signs installation | 4 | each | $1,000.00 | $4,000.00 | Construction |
| Storm sewer pipe installation | 500 | linear foot | $150.00 | $75,000.00 | Construction |
| Catch basins installation | 10 | each | $2,500.00 | $25,000.00 | Construction |
| Bridge railing installation | 500 | linear foot | $200.00 | $100,000.00 | Construction |
| Embankment placement | 20000 | cubic yard | $50.00 | $1,000,000.00 | Construction |
| Crushed surfacing base placement | 10000 | ton | $80.00 | $800,000.00 | Construction |
| Estimated Bid Value | $10,500,000.00 | ||||