| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Site opening with safety measures | 1 | lot | $1,500.00 | $1,500.00 | Construction |
| Removal of existing piping | 1 | lot | $1,000.00 | $1,000.00 | Construction |
| Reinstallation of existing piping | 1 | lot | $1,500.00 | $1,500.00 | Construction |
| Removal of existing 5000 Lt water tanks | 3 | each | $500.00 | $1,500.00 | Construction |
| Disposal of existing 5000 Lt water tanks | 3 | each | $300.00 | $900.00 | Construction |
| Supply and installation of new 5000 Lt water tank with insulating factors | 3 | each | $7,500.00 | $22,500.00 | Construction |
| Installation of new tank components (per tank) | 3 | each | $500.00 | $1,500.00 | Construction |
| Testing of new water tank system | 1 | lot | $1,000.00 | $1,000.00 | Construction |
| Estimated Bid Value | $31,500.00 | ||||
Sign up free to see the agency name, 2 documents, contact info, and the original bid posting link.