| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal of Existing Above Ground Fuel Storage Tanks | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Removal of Existing Fuel Pumps and Associated Piping | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Disposal of Hazardous Materials (Fuel, Contaminated Soil, etc.) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| New Above Ground Fuel Storage Tanks (e.g., 10,000-gallon double-wall steel tank) | 2 | each | $40,000.00 | $80,000.00 | Construction |
| New Fuel Dispensing Pumps (e.g., commercial grade, high-flow) | 2 | each | $7,500.00 | $15,000.00 | Construction |
| Installation of New Fuel Storage Tanks and Pumps | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| New Fuel Piping, Electrical, and Control Systems | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Site Preparation and Restoration (e.g., concrete pads, grading) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Permitting, Engineering, and Project Management | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Estimated Bid Value | $250,000.00 | ||||