| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal of existing control tower bridge crane and trolley | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| New control tower bridge crane (materials and procurement) | 1 | each | $60,000.00 | $60,000.00 | Construction |
| New control tower trolley (materials and procurement) | 1 | each | $20,000.00 | $20,000.00 | Construction |
| Installation of new control tower bridge crane and trolley | 1 | lot | $35,000.00 | $35,000.00 | Construction |
| Project Management, Supervision, Quality Control, and Communication | 1 | lot | $10,000.00 | $10,000.00 | Professional Services |
| Estimated Bid Value | $150,000.00 | ||||