| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Site Preparation and Earthwork (clearing, grubbing, grading) | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Road and Parking Area Construction/Resurfacing | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Campground Site Improvements (e.g., tent pads, picnic tables, fire rings) | 50 | each | $2,500.00 | $125,000.00 | Construction |
| Restroom/Vault Toilet Construction/Renovation | 3 | each | $75,000.00 | $225,000.00 | Construction |
| Water System Installation/Upgrade (e.g., potable water lines, spigots) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Wastewater System Installation/Upgrade (e.g., septic, greywater) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Signage and Interpretive Panels | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Accessibility Improvements (ADA compliance, ramps, pathways) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Drainage Improvements | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Demolition and Debris Removal | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Estimated Bid Value | $1,500,000.00 | ||||