| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Labor for Sewer Pump Station Control Relocation | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Tools and Equipment for Sewer Pump Station Control Relocation | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Miscellaneous Materials for Sewer Pump Station Control Relocation | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Supervision for Sewer Pump Station Control Relocation | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Estimated Bid Value | $50,000.00 | ||||