| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| LED Runway Edge Lights (L-862E equivalent) | 200 | each | $750.00 | $150,000.00 | Construction |
| LED Runway Threshold Lights (L-862T equivalent) | 20 | each | $850.00 | $17,000.00 | Construction |
| LED Runway End Lights (L-862E equivalent) | 20 | each | $850.00 | $17,000.00 | Construction |
| LED Taxiway Edge Lights (L-861T equivalent) | 100 | each | $600.00 | $60,000.00 | Construction |
| Constant Current Regulators (CCR) for LED Lighting | 5 | each | $15,000.00 | $75,000.00 | Construction |
| Runway Lighting Control System Upgrade (PLC/SCADA) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Electrical Conduit and Wiring (Underground) | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Trenching and Backfilling Services | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Installation Services for Runway Lighting System | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Testing and Commissioning Services for Runway Lighting System | 1 | lot | $50,000.00 | $50,000.00 | Professional Services |
| Project Management and Engineering Services | 1 | lot | $150,000.00 | $150,000.00 | Professional Services |
| Disposal of Old Lighting Equipment | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Site Preparation and Restoration | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Safety and Environmental Compliance | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Estimated Bid Value | $1,500,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 3 documents, contracting-officer contacts and AI response outlines.