| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Roadway Excavation (Common) | 2000 | cubic yard | $45.00 | $90,000.00 | Construction |
| Granular Borrow (Subbase) | 3000 | cubic yard | $55.00 | $165,000.00 | Construction |
| Hot Mix Asphalt (Surface Course) | 1500 | ton | $150.00 | $225,000.00 | Construction |
| Hot Mix Asphalt (Base Course) | 2000 | ton | $140.00 | $280,000.00 | Construction |
| Drainage Culvert Installation (18-inch CMP) | 100 | linear foot | $120.00 | $12,000.00 | Construction |
| Guardrail Installation (Steel Beam) | 200 | linear foot | $80.00 | $16,000.00 | Construction |
| Traffic Control and Detour Management | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Erosion Control Measures (Silt Fence, Hay Bales) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Pavement Markings (Thermoplastic) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Mobilization and Demobilization | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Project Management and Supervision (0.42 miles) | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Environmental Compliance and Permitting | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Contingency (10% of estimated construction costs) | 1 | lot | $187,000.00 | $187,000.00 | Other |
| Estimated Bid Value | $1,260,000.00 | ||||