| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Asphalt Pavement Repair (Pothole/Patching) | 5000 | square yard | $45.00 | $225,000.00 | Construction |
| Asphalt Overlay (2-inch thickness) | 10000 | square yard | $30.00 | $300,000.00 | Construction |
| Full Depth Asphalt Pavement Replacement | 2000 | square yard | $75.00 | $150,000.00 | Construction |
| Concrete Curb and Gutter Repair/Replacement | 1500 | linear foot | $60.00 | $90,000.00 | Construction |
| Parking Lot Striping (Standard) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Accessible Parking Space Striping and Signage | 20 | each | $500.00 | $10,000.00 | Construction |
| Storm Drain Inlet Repair/Replacement | 10 | each | $2,500.00 | $25,000.00 | Construction |
| Drainage Improvements (Minor Grading/Swales) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Site Preparation and Demolition (Existing Pavement) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Traffic Control and Safety Measures | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $150,000.00 | $150,000.00 | Professional Services |
| Mobilization/Demobilization | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Contingency (10% of estimated construction costs) | 1 | lot | $130,000.00 | $130,000.00 | Other |
| Estimated Bid Value | $1,500,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 8 documents, contracting-officer contacts and AI response outlines.