This bid is for a design-build construction project to install a new, independent HVAC system for the 97th IS facility at Offutt Air Force Base, Nebraska.
Line Items
Item
Qty
Unit
Est. Unit Price
Est. Total
Category
Design-Build Services for HVAC System
1
lot
$50,000.00
$50,000.00
Construction
New Air Handling Unit (AHU) - 97th IS
1
each
$75,000.00
$75,000.00
Construction
HVAC System Installation Labor
1
lot
$100,000.00
$100,000.00
Construction
Ductwork and Ventilation System Components
1
lot
$40,000.00
$40,000.00
Construction
Electrical System Upgrades and Connections for HVAC
1
lot
$35,000.00
$35,000.00
Construction
HVAC Control System and Integration
1
lot
$25,000.00
$25,000.00
Construction
Permitting, Testing, and Commissioning
1
lot
$25,000.00
$25,000.00
Construction
Estimated Bid Value
$350,000.00