| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Site Preparation and Earthwork (Clearing, grubbing, excavation, grading) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Asphalt Paving (including subbase and base course materials, installation) | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Storm Drainage System Installation (catch basins, piping, detention/retention) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Electrical Infrastructure (lighting, power outlets, conduit, wiring for lot) | 1 | lot | $125,000.00 | $125,000.00 | Construction |
| Plumbing Infrastructure (water lines, sewer lines, drains for lot) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Mechanical Infrastructure (HVAC components, ventilation for lot, if applicable) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Striping and Signage (parking lot markings, traffic signs) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $50,000.00 | $50,000.00 | Professional Services |
| Estimated Bid Value | $750,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 4 documents, contracting-officer contacts and AI response outlines.