| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Project Management and Engineering for 8-inch Steam Pipeline Termination and Isolation | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Labor for 8-inch Steam Pipeline Termination and Isolation (including pipefitters, welders, laborers) | 240 | hour | $85.00 | $20,400.00 | Construction |
| Materials for 8-inch Steam Pipeline Termination and Isolation (e.g., blind flanges, gaskets, bolts, welding rods, insulation) | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Heavy Equipment Rental (e.g., pipe stands, lifting equipment, welding machines) | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Safety Planning and Implementation for Pipeline Work | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Disposal of Removed Pipeline Sections and Associated Waste | 1 | lot | $7,000.00 | $7,000.00 | Construction |
| Post-Termination Inspection and Documentation | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Contingency for Unforeseen Issues | 1 | lot | $5,100.00 | $5,100.00 | Construction |
| Estimated Bid Value | $75,000.00 | ||||