| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Sidewalk Construction (Concrete) | 2000 | linear feet | $40.00 | $80,000.00 | Construction |
| Curbing Installation (Granite or Concrete) | 2000 | linear feet | $30.00 | $60,000.00 | Construction |
| Excavation and Grading | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Drainage Improvements (Catch Basins, Pipes) | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Asphalt Paving (Driveway Aprons, Roadway Tie-ins) | 500 | square yards | $50.00 | $25,000.00 | Construction |
| Traffic Control and Management | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Erosion Control Measures | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Landscaping and Restoration (Loam, Seed, Mulch) | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $50,000.00 | $50,000.00 | Professional Services |
| Permitting and Regulatory Compliance | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Estimated Bid Value | $350,000.00 | ||||