| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Lot Cleaning at 104 Fleishman St. | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Asbestos Abatement at 104 Fleishman St. | 1 | project | $20,000.00 | $20,000.00 | Construction |
| Demolition at 104 Fleishman St. | 1 | project | $30,000.00 | $30,000.00 | Construction |
| Lot Cleaning at 419 Hall St. | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Asbestos Abatement at 419 Hall St. | 1 | project | $20,000.00 | $20,000.00 | Construction |
| Demolition at 419 Hall St. | 1 | project | $30,000.00 | $30,000.00 | Construction |
| Lot Cleaning at 429 Chatham St. | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Asbestos Abatement at 429 Chatham St. | 1 | project | $20,000.00 | $20,000.00 | Construction |
| Demolition at 429 Chatham St. | 1 | project | $30,000.00 | $30,000.00 | Construction |
| Lot Cleaning at 1299 Bingham Dr. | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Asbestos Abatement at 1299 Bingham Dr. | 1 | project | $20,000.00 | $20,000.00 | Construction |
| Demolition at 1299 Bingham Dr. | 1 | project | $30,000.00 | $30,000.00 | Construction |
| Lot Cleaning at 5329 Murchison Rd. | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Asbestos Abatement at 5329 Murchison Rd. | 1 | project | $20,000.00 | $20,000.00 | Construction |
| Demolition at 5329 Murchison Rd. | 1 | project | $30,000.00 | $30,000.00 | Construction |
| Estimated Bid Value | $375,000.00 | ||||