| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition and Site Preparation (Restrooms) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| New Plumbing Fixtures (Toilets, Sinks, Urinals) | 10 | each | $1,500.00 | $15,000.00 | Construction |
| Plumbing Rough-in and Finish Work | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Electrical Work (Lighting, Outlets, Wiring) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| HVAC Modifications/Upgrades (Ventilation) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Tile Flooring Installation | 1000 | sq ft | $25.00 | $25,000.00 | Construction |
| Wall Finishes (Paint, Wall Covering) | 2000 | sq ft | $10.00 | $20,000.00 | Construction |
| Restroom Partitions | 5 | each | $2,000.00 | $10,000.00 | Construction |
| Vanities and Countertops | 4 | each | $2,500.00 | $10,000.00 | Construction |
| Mirrors and Accessories (Soap Dispensers, Hand Dryers) | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Doors and Hardware | 4 | each | $1,500.00 | $6,000.00 | Construction |
| Ceiling System (Acoustical Tile or Drywall) | 1000 | sq ft | $15.00 | $15,000.00 | Construction |
| Fire Protection System Modifications (if required) | 1 | lot | $7,000.00 | $7,000.00 | Construction |
| General Contractor Overhead and Profit | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $30,000.00 | $30,000.00 | Professional Services |
| Permits, Fees, and Inspections | 1 | lot | $10,000.00 | $10,000.00 | Professional Services |
| Contingency (10% of estimated construction costs) | 1 | lot | $39,000.00 | $39,000.00 | Other |
| Estimated Bid Value | $350,000.00 | ||||