| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| York 2075 Chiller (100-ton) | 1 | each | $80,000.00 | $80,000.00 | Facilities |
| Chiller Decommissioning Services | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Chiller Relocation Services | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Chiller Installation Services | 1 | lot | $30,000.00 | $30,000.00 | Facilities |
| Piping and Fittings for Chiller Installation | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Electrical Wiring and Connections for Chiller | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Supervision and Project Management | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Estimated Bid Value | $150,000.00 | ||||