| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Headworks Rebuild Project Management and Engineering Services | 1 | lot | $350,000.00 | $350,000.00 | Professional Services |
| Site Preparation and Demolition (existing structures, earthwork) | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Concrete Foundations and Structures (new headworks facility) | 1 | lot | $800,000.00 | $800,000.00 | Construction |
| Piping and Valves (water conveyance systems) | 1 | lot | $600,000.00 | $600,000.00 | Construction |
| Mechanical Equipment Installation (screens, gates, pumps, etc.) | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Electrical Systems and Controls (power, instrumentation, SCADA integration) | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Site Restoration and Landscaping | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Testing, Commissioning, and Startup Services | 1 | lot | $200,000.00 | $200,000.00 | Professional Services |
| Estimated Bid Value | $3,500,000.00 | ||||