| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Precast Prefabricated Four (4) Room Unisex, ADA Accessible Restroom and Shower Building | 1 | each | $180,000.00 | $180,000.00 | Construction |
| 10,000-Gallon Capacity Septic Holding Tank | 1 | each | $30,000.00 | $30,000.00 | Construction |
| Equipment for Comfort Station and Septic Tank Installation | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Labor for Comfort Station and Septic Tank Installation | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Permits for Construction Project | 1 | lot | $5,000.00 | $5,000.00 | Professional Services |
| Materials for Comfort Station and Septic Tank Installation (excluding main units) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Estimated Bid Value | $300,000.00 | ||||