| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal and disposal of non-functional ductless heat pump A/C systems | 16 | each | $300.00 | $4,800.00 | Construction |
| Installation of new cooling-only split A/C systems (including disconnecting/reconnecting power and refrigerant lines, testing) | 16 | each | $3,500.00 | $56,000.00 | Construction |
| New cooling-only split A/C systems (equipment cost) | 16 | each | $2,500.00 | $40,000.00 | Construction |
| Installation of external condensation pumps | 16 | each | $200.00 | $3,200.00 | Construction |
| External condensation pumps (equipment cost) | 16 | each | $100.00 | $1,600.00 | Construction |
| Purge and test existing drain lines | 16 | each | $150.00 | $2,400.00 | Construction |
| Replacement of drain lines (as needed, estimated per unit) | 16 | each | $250.00 | $4,000.00 | Construction |
| Estimated Bid Value | $112,000.00 | ||||