| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Construction Manager-at-Risk (CMR) Pre-Construction Services | 1 | lot | $3,500,000.00 | $3,500,000.00 | Professional Services |
| Construction Manager-at-Risk (CMR) Construction Services for New Park Development | 1 | lot | $31,500,000.00 | $31,500,000.00 | Construction |
| Park entry and monument signage | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Electrical access gate(s) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Paved Roadways including low water crossing(s) | 1 | lot | $5,000,000.00 | $5,000,000.00 | Construction |
| Gravel Roadways | 1 | lot | $2,000,000.00 | $2,000,000.00 | Construction |
| Parkwide directional signage | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Park Headquarters building | 1 | each | $1,500,000.00 | $1,500,000.00 | Construction |
| Staff residences | 3 | each | $400,000.00 | $1,200,000.00 | Construction |
| Park host sites | 5 | each | $50,000.00 | $250,000.00 | Construction |
| Maintenance yard and supporting buildings | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Trailheads | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Multi-use trails | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Picnic areas | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Group pavilion(s) | 2 | each | $250,000.00 | $500,000.00 | Construction |
| Amphitheater | 1 | each | $750,000.00 | $750,000.00 | Construction |
| Nature Center building | 1 | each | $2,000,000.00 | $2,000,000.00 | Construction |
| Playground | 1 | each | $300,000.00 | $300,000.00 | Construction |
| Wildlife viewing areas | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Day Use Restrooms | 3 | each | $300,000.00 | $900,000.00 | Construction |
| Day Use Parking areas | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Developed camping areas | 1 | lot | $2,500,000.00 | $2,500,000.00 | Construction |
| Primitive camping areas | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Mini-cabins | 10 | each | $150,000.00 | $1,500,000.00 | Construction |
| Screened shelters | 15 | each | $75,000.00 | $1,125,000.00 | Construction |
| Overnight Facilities Restrooms | 5 | each | $300,000.00 | $1,500,000.00 | Construction |
| Overnight Facilities Parking areas | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Public water system infrastructure | 1 | lot | $2,000,000.00 | $2,000,000.00 | Construction |
| Wastewater treatment facilities infrastructure | 1 | lot | $2,500,000.00 | $2,500,000.00 | Construction |
| Electrical infrastructure | 1 | lot | $1,800,000.00 | $1,800,000.00 | Construction |
| Telecommunications infrastructure | 1 | lot | $750,000.00 | $750,000.00 | Telecommunications |
| Estimated Bid Value | $35,000,000.00 | ||||