| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Concrete Curbs | 5000 | linear feet | $35.00 | $175,000.00 | Construction |
| Concrete Sidewalks | 10000 | square feet | $15.00 | $150,000.00 | Construction |
| Concrete Driveways | 5000 | square feet | $20.00 | $100,000.00 | Construction |
| Concrete Retaining Walls - Combination Type | 500 | linear feet | $150.00 | $75,000.00 | Construction |
| Wheelchair Ramps (ADA compliant) | 50 | each | $3,000.00 | $150,000.00 | Construction |
| Minor Asphalt Milling and Replacement | 10000 | square yards | $25.00 | $250,000.00 | Construction |
| Removing and Relocating Mailboxes | 50 | each | $200.00 | $10,000.00 | Construction |
| Topsoil Installation | 500 | cubic yards | $75.00 | $37,500.00 | Construction |
| Sodding | 10000 | square feet | $1.50 | $15,000.00 | Construction |
| Striping (Pavement Markings) | 2000 | linear feet | $5.00 | $10,000.00 | Construction |
| Elevated Sidewalks | 1000 | square feet | $30.00 | $30,000.00 | Construction |
| Sidewalk Pipe Railing | 200 | linear feet | $75.00 | $15,000.00 | Construction |
| Adjusting Existing Meter Boxes | 50 | each | $300.00 | $15,000.00 | Construction |
| Adjusting Existing Valve Boxes | 50 | each | $300.00 | $15,000.00 | Construction |
| Adjusting Existing Manholes | 20 | each | $800.00 | $16,000.00 | Construction |
| Tree Pruning | 30 | each | $400.00 | $12,000.00 | Facilities |
| Tree Removal and/or Replacement | 20 | each | $1,500.00 | $30,000.00 | Facilities |
| Site Condition Remediation (Miscellaneous) | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Estimated Bid Value | $1,500,000.00 | ||||