| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Dewatering the site | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Providing erosion control | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Excavating existing dike soil and stockpiling | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Removing existing 36" diameter dike culvert and anti-seep collars (if suitable for reuse) | 1 | each | $10,000.00 | $10,000.00 | Construction |
| Resetting existing 36" diameter dike culvert and anti-seep collars | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Placing riprap around culvert outlet | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Placing nonwoven geotextile around culvert outlet | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Backfilling and compacting the dike | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| New 36" diameter culvert and anti-seep collars (if existing not salvageable) | 1 | each | $50,000.00 | $50,000.00 | Construction |
| Installation of new 36" diameter culvert and anti-seep collars (if existing not salvageable) | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Project Management, Mobilization, Demobilization, and Site Supervision | 1 | lot | $115,000.00 | $115,000.00 | Construction |
| Estimated Bid Value | $375,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 8 documents, contracting-officer contacts and AI response outlines.