| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal of existing DC battery system | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Disposal of existing DC battery system (including hazardous waste handling) | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Procurement and installation of new DC battery system (including batteries, racks, cabling, and associated hardware) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Testing and commissioning of new DC battery system | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Project management and phase-in services | 1 | lot | $5,000.00 | $5,000.00 | Professional Services |
| Estimated Bid Value | $75,000.00 | ||||