| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition of existing failed concrete and damaged stair components | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Removal of deteriorated #4 reinforcement steel | 1 | lot | $2,500.00 | $2,500.00 | Construction |
| Reconstruction of loading dock platform and stair system to VA structural dimensions | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Installation of new structural reinforcement (rebar and steel dowels) tied into existing concrete | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Placement of 3500 PSI concrete for the platform, stairs, and edge reconstruction | 1 | lot | $12,000.00 | $12,000.00 | Construction |
| Installation of VA-required safety bumpers and yellow tread markings on stairs | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Application of required finishing and concrete sealant | 1 | lot | $3,000.00 | $3,000.00 | Construction |
| Labor, materials, tools, equipment, travel, qualified service technicians, and supervision for project completion | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Estimated Bid Value | $62,500.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 1 document, contracting-officer contacts and AI response outlines.