| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Staking camping spurs from plans | 1 | lot | $2,500.00 | $2,500.00 | Construction |
| Stripping turf from campsite areas | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Earthwork for campsite development (excavation, grading) | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Excavating campsite spurs and social areas to sub-grade | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Installation and compaction of aggregate base course for spurs and social areas | 1 | lot | $35,000.00 | $35,000.00 | Construction |
| Installation and compaction of aggregate surface course for spurs and social areas | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Grading for proper drainage around spurs and social areas | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Restoring disturbed areas with topsoil, seed, and mulch | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Disposal of stripped turf and excess earthen materials to on-site locations | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Estimated Bid Value | $150,000.00 | ||||