| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Replacement of grounding and high-level shut-off valves for F-24 Tank 1 | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Replacement of grounding and high-level shut-off valves for F-24 Tank 2 | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Extension of tank catwalk platform | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Installation of check valve on relief discharge into Tank 2 | 1 | each | $7,500.00 | $7,500.00 | Construction |
| Installation of truck offload meter | 1 | each | $12,000.00 | $12,000.00 | Construction |
| Installation of visual fuel flow indicator | 1 | each | $3,000.00 | $3,000.00 | Construction |
| Installation of eyewash station | 1 | each | $4,000.00 | $4,000.00 | Construction |
| Installation of filter separator maintenance platform for truck offload/fillstand | 1 | lot | $18,000.00 | $18,000.00 | Construction |
| Integrated truck overfill prevention system | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Integrated truck ground verification system | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Installation of protective pipe bollards for offload/fillstand | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Replacement of equipment shelter ground system | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Ground verification system for offload operations | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Supply, installation, and testing of Automatic Tank Gauging (ATG) system on fuel storage Tank 1 | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Supply, installation, and testing of Automatic Tank Gauging (ATG) system on fuel storage Tank 2 | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Project Management, Engineering, and Site Supervision for Fuel System Repairs | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Estimated Bid Value | $425,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 4 documents, contracting-officer contacts and AI response outlines.