| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Dredged material placement with forest rehabilitation | 1 | project phase | $15,000,000.00 | $15,000,000.00 | Construction |
| Dredging for overwintering habitat and sediment reduction | 1 | project phase | $10,000,000.00 | $10,000,000.00 | Construction |
| Bank stabilization | 1 | project phase | $5,000,000.00 | $5,000,000.00 | Construction |
| River training structures construction | 1 | project phase | $7,500,000.00 | $7,500,000.00 | Construction |
| Cut-through channel modification | 1 | project phase | $3,500,000.00 | $3,500,000.00 | Construction |
| Cedar Creek modification | 1 | project phase | $4,000,000.00 | $4,000,000.00 | Construction |
| Estimated Bid Value | $45,000,000.00 | ||||