| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal and disposal of existing heating and cooling system pumps and motors | 4 | each | $750.00 | $3,000.00 | Construction |
| Removal and disposal of existing Variable Frequency Drives (VFDs) | 5 | each | $300.00 | $1,500.00 | Construction |
| New heating and cooling system pumps and associated motors (supply and install) | 4 | each | $10,000.00 | $40,000.00 | Construction |
| New Variable Frequency Drives (VFDs) (supply and install) | 5 | each | $4,000.00 | $20,000.00 | Construction |
| Integration with Johnson Controls Metasys building automation system | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Certified third-party Testing and Balancing (TAB) process | 1 | lot | $10,000.00 | $10,000.00 | Professional Services |
| Project Management and Supervision (210-day performance period) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Submittals and Documentation (equipment data, TAB reports, Metasys reports, safety plans, schedules, O&M documentation) | 1 | lot | $5,000.00 | $5,000.00 | Professional Services |
| Permits and Licenses (plumbing and electrical) | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Estimated Bid Value | $120,000.00 | ||||