| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Full Start-Up and Commissioning of Data Center Environmental Control Systems | 1 | lot | $75,000.00 | $75,000.00 | Facilities |
| Replacement of Eaton Uninterruptible Power Supply (UPS) System Batteries | 1 | lot | $30,000.00 | $30,000.00 | Facilities |
| EPA-Compliant Disposal of Used UPS Batteries | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Estimated Bid Value | $115,000.00 | ||||