| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| 20'x60' steel oil pipe horse corral with three pens (base project) | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Concrete for post embedment (base project) | 1 | lot | $1,500.00 | $1,500.00 | Construction |
| Temporary traffic control measures (base project) | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Sign stating horse corrals are closed to public | 1 | each | $200.00 | $200.00 | Construction |
| Optional: 20'x60' steel oil pipe horse corral with three pens (Option #1) | 1 | each | $18,000.00 | $18,000.00 | Construction |
| Optional: Hitching rail (Option #2) | 1 | each | $800.00 | $800.00 | Construction |
| Estimated Bid Value | $47,500.00 | ||||