| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Hazardous material/debris abatement and removal (crawl space) | 2 | building | $250,000.00 | $500,000.00 | Construction |
| Partial removal/demolition of exterior building envelope and interior walls (~75%) | 2 | building | $750,000.00 | $1,500,000.00 | Construction |
| Removal of building mechanical-electrical systems (~90%) | 2 | building | $500,000.00 | $1,000,000.00 | Construction |
| Removal of existing roof EPDM system (excluding framing) | 2 | building | $100,000.00 | $200,000.00 | Construction |
| New exterior envelope installation | 2 | building | $1,500,000.00 | $3,000,000.00 | Construction |
| New building mechanical-electrical systems installation | 2 | building | $1,250,000.00 | $2,500,000.00 | Construction |
| New Thermoplastic Polyolefin (TPO) Roof system installation | 2 | building | $150,000.00 | $300,000.00 | Construction |
| Painting of building exteriors | 2 | building | $100,000.00 | $200,000.00 | Construction |
| Site work coordination for new utility connections | 1 | lot | $800,000.00 | $800,000.00 | Construction |
| Site work coordination for shared construction boundaries | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Estimated Bid Value | $10,500,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 1 document, contracting-officer contacts and AI response outlines.