| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mold Remediation Services (Base: Building 269 excluding rooms 14 and 15) | 1 | JOB | $30,000.00 | $30,000.00 | Facilities |
| Demo and replace 300 damaged and moisture-stained ceiling tiles (24" x 24" flat square lay-in) | 300 | each | $15.00 | $4,500.00 | Facilities |
| Mold Remediation Services (Option 1: Offices 1-7, approx. 1760 SF) | 1 | JOB | $15,000.00 | $15,000.00 | Facilities |
| Remove and clean all content items (Offices 1-7) | 1 | JOB | $2,000.00 | $2,000.00 | Facilities |
| HEPA vacuum and wet wipe inside and outside all wood cabinets (Offices 1-7) | 1 | JOB | $1,500.00 | $1,500.00 | Facilities |
| Clean carpets (Offices 1-7) | 1760 | SF | $1.50 | $2,640.00 | Facilities |
| HEPA vacuum and wet wipe all metal ceiling diffusers top and bottom (Offices 1-7) | 1 | JOB | $500.00 | $500.00 | Facilities |
| Mold Remediation Services (Option 2: Building 269 excluding offices 1-7, 14, and 15, approx. 13,000 SF) | 1 | JOB | $25,000.00 | $25,000.00 | Facilities |
| Remove and clean all content items (Building 269 excluding offices 1-7, 14, and 15) | 1 | JOB | $3,000.00 | $3,000.00 | Facilities |
| HEPA vacuum and wet wipe inside and outside all wood cabinets (Building 269 excluding offices 1-7, 14, and 15) | 1 | JOB | $2,500.00 | $2,500.00 | Facilities |
| Clean carpets (Building 269 excluding offices 1-7, 14, and 15) | 13000 | SF | $1.50 | $19,500.00 | Facilities |
| HEPA vacuum and wet wipe all metal ceiling diffusers top and bottom (Building 269 excluding offices 1-7, 14, and 15) | 1 | JOB | $1,000.00 | $1,000.00 | Facilities |
| Mold Remediation Services (Option 3: Room 14-14I, approx. 2000 SF - Demolition focus) | 1 | JOB | $20,000.00 | $20,000.00 | Construction |
| Demo all content items (Room 14-14I) | 1 | JOB | $1,500.00 | $1,500.00 | Construction |
| Demo all wood base trim and crown molding from all walls (Room 14-14I) | 1 | JOB | $1,000.00 | $1,000.00 | Construction |
| Demo wallpaper partition walls throughout the offices (Room 14-14I) | 1 | JOB | $1,200.00 | $1,200.00 | Construction |
| Demo and replace lower 2' of drywall on south wall in hallway adjacent to conference room 15 (Room 14-14I) | 1 | JOB | $1,800.00 | $1,800.00 | Construction |
| Demo and replace all other remaining drywall (Room 14-14I) | 1 | JOB | $5,000.00 | $5,000.00 | Construction |
| Demo carpets throughout the offices (Room 14-14I) | 2000 | SF | $1.00 | $2,000.00 | Construction |
| Clean all door and window components (Room 14-14I) | 1 | JOB | $800.00 | $800.00 | Facilities |
| Demo all ceiling tiles (Room 14-14I) | 1 | JOB | $1,500.00 | $1,500.00 | Construction |
| HEPA vacuum and wet wipe all metal ceiling diffusers top and bottom (Room 14-14I) | 1 | JOB | $600.00 | $600.00 | Facilities |
| Demo all expandable fiberglass HVAC ducts above ceilings (Room 14-14I) | 1 | JOB | $2,000.00 | $2,000.00 | Construction |
| Clean inside and outside metal HVAC ducts above ceilings (Room 14-14I) | 1 | JOB | $1,500.00 | $1,500.00 | Facilities |
| Mold Remediation Services (Option 4: Room 15A-B, approx. 1150 SF - Cleaning/Limited Demo) | 1 | JOB | $10,000.00 | $10,000.00 | Facilities |
| Remove and clean all content items (Room 15A-B) | 1 | JOB | $1,000.00 | $1,000.00 | Facilities |
| Demo and replace all cove base on all walls (approx. 175 LF) (Room 15A-B) | 175 | LF | $10.00 | $1,750.00 | Construction |
| HEPA vacuum and wet wipe drywall walls floor to ceiling (Room 15A-B) | 1 | JOB | $1,500.00 | $1,500.00 | Facilities |
| Clean the carpet (Room 15A-B) | 1150 | SF | $1.50 | $1,725.00 | Facilities |
| Clean inside and outside of the wood cabinets (Room 15A-B) | 1 | JOB | $800.00 | $800.00 | Facilities |
| Clean all door and window components (Room 15A-B) | 1 | JOB | $500.00 | $500.00 | Facilities |
| HEPA vacuum and wet wipe all metal ceiling diffusers top and bottom (Room 15A-B) | 1 | JOB | $400.00 | $400.00 | Facilities |
| Mold Remediation Services (Option 5: Room 15A-B, approx. 1150 SF - Extensive Demolition) | 1 | JOB | $15,000.00 | $15,000.00 | Construction |
| Remove and clean all content items (Room 15A-B, Option 5) | 1 | JOB | $1,000.00 | $1,000.00 | Facilities |
| Demo all cove base on all walls (Room 15A-B, Option 5) | 1 | JOB | $800.00 | $800.00 | Construction |
| Demo and replace drywall walls floor to ceiling (Room 15A-B, Option 5) | 1 | JOB | $4,000.00 | $4,000.00 | Construction |
| Demo the carpet (Room 15A-B, Option 5) | 1150 | SF | $1.00 | $1,150.00 | Construction |
| Demo ceiling tiles (Room 15A-B, Option 5) | 1 | JOB | $800.00 | $800.00 | Construction |
| Clean inside and outside of the wood cabinets (Room 15A-B, Option 5) | 1 | JOB | $800.00 | $800.00 | Facilities |
| Clean all door and window components (Room 15A-B, Option 5) | 1 | JOB | $500.00 | $500.00 | Facilities |
| HEPA vacuum and wet wipe all metal ceiling diffusers top and bottom (Room 15A-B, Option 5) | 1 | JOB | $400.00 | $400.00 | Facilities |
| Estimated Bid Value | $150,000.00 | ||||