| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Shoreline Restoration Project Management and Engineering | 1 | lot | $500,000.00 | $500,000.00 | Professional Services |
| Mobilization and Demobilization of Equipment and Personnel | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Dredging and Sediment Placement (estimated 100,000 cubic yards) | 100000 | cubic yard | $25.00 | $2,500,000.00 | Construction |
| Revetment or Breakwater Construction (e.g., rock, concrete structures) | 500 | linear foot | $1,000.00 | $500,000.00 | Construction |
| Vegetative Planting and Habitat Restoration (e.g., marsh grasses) | 5 | acre | $50,000.00 | $250,000.00 | Construction |
| Erosion Control Measures (e.g., geotextiles, coir logs) | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Environmental Monitoring and Compliance | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Site Preparation and Grading | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Contingency and Miscellaneous Costs | 1 | lot | $550,000.00 | $550,000.00 | Other |
| Estimated Bid Value | $5,000,000.00 | ||||