| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization and Demobilization of Dredging Equipment | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Hydraulic Pipeline Dredging (Base Work) - Sandy Material | 101000 | cubic yard | $20.00 | $2,020,000.00 | Construction |
| Direct Placement of Dredged Material (Base Work) in Government-furnished Shoreline Placement Area | 101000 | cubic yard | $5.00 | $505,000.00 | Construction |
| Hydraulic Pipeline Dredging (Optional Work) - Additional Sandy Material | 29000 | cubic yard | $20.00 | $580,000.00 | Construction |
| Direct Placement of Dredged Material (Optional Work) in Government-furnished Shoreline Placement Area | 29000 | cubic yard | $5.00 | $145,000.00 | Construction |
| Estimated Bid Value | $3,000,000.00 | ||||