| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Site Preparation and Demolition (existing structures, debris removal) | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Dredging and Sediment Removal | 15000 | cubic yard | $75.00 | $1,125,000.00 | Construction |
| Shoreline Stabilization (e.g., riprap, revetment, gabions) | 5000 | linear foot | $400.00 | $2,000,000.00 | Construction |
| Bulkhead/Seawall Construction or Repair | 2000 | linear foot | $1,000.00 | $2,000,000.00 | Construction |
| Pier/Dock Repair or Replacement | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Beach Nourishment/Sand Placement | 10000 | cubic yard | $60.00 | $600,000.00 | Construction |
| Environmental Mitigation and Restoration (e.g., wetland creation, habitat restoration) | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Stormwater Management Improvements | 1 | lot | $800,000.00 | $800,000.00 | Construction |
| Landscaping and Revegetation | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Access Roads and Pathways Construction/Repair | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Utility Relocation/Installation (if required) | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Project Management and Engineering Services | 1 | lot | $1,500,000.00 | $1,500,000.00 | Professional Services |
| Permitting and Regulatory Compliance | 1 | lot | $300,000.00 | $300,000.00 | Professional Services |
| Contingency (10-15% of construction costs) | 1 | lot | $1,775,000.00 | $1,775,000.00 | Other |
| Estimated Bid Value | $15,000,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds contracting-officer contacts and AI response outlines.
Sign Up Free → Already have an account? Log in