SOURCES SOUGHT: Carters Reregulation Dam Short Term Repairs

Estimated Value: $7,500,000
Open New 15 days left AlabamaConstructionrfi
Oct 5, 2026
Oct 20, 2026 7:00 PM
Construction
rfi
237990
Small Business
AI Summary
This bid is a sources sought notice for a firm-fixed-price construction contract to perform structural concrete and gate repairs on the spillway at the Carters Reregulation Dam, addressing concrete expansion due to Alkali-Silica Reactivity (ASR) and replacing gate seals.
Line Items
ItemQtyUnitEst. Unit PriceEst. TotalCategory
Structural concrete demolition of existing pier stoplog slots 1 lot $750,000.00 $750,000.00 Construction
Installation of new steel stoplog guides and embedded seal plates 1 lot $1,000,000.00 $1,000,000.00 Construction
Placement of specialized shrinkage-compensating concrete 1 lot $1,500,000.00 $1,500,000.00 Construction
Recessing of side seal plates 1 lot $250,000.00 $250,000.00 Construction
Replacement of side and bottom seals on Tainter gates 4 each $500,000.00 $2,000,000.00 Construction
Replacement of seals on stop logs 8 each $125,000.00 $1,000,000.00 Construction
Design, fabrication, and installation of Temporary Dewatering Structures (TDS)/cofferdams 1 lot $750,000.00 $750,000.00 Construction
Design, fabrication, and installation of temporary gate support shoring 1 lot $250,000.00 $250,000.00 Construction
Estimated Bid Value$7,500,000.00

Want the full details?

Sign up free to see the agency name and the original bid posting link. Pro adds the 4 documents, contracting-officer contacts and AI response outlines.

📎 oppMgmtLink.pdf View
📎 index.pdf View
📎 PIEE_Solicitation_Module_Vendor_Access_Instructions.pdf View
+1 more
Sign Up Free → Already have an account? Log in

Browse More Bids

Bids in AlabamaConstruction BidsRFI BidsClosing Soon All Bids