| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Structural concrete demolition of existing pier stoplog slots | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Installation of new steel stoplog guides and embedded seal plates | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Placement of specialized shrinkage-compensating concrete | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Recessing of side seal plates | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Replacement of side and bottom seals on Tainter gates | 4 | each | $500,000.00 | $2,000,000.00 | Construction |
| Replacement of seals on stop logs | 8 | each | $125,000.00 | $1,000,000.00 | Construction |
| Design, fabrication, and installation of Temporary Dewatering Structures (TDS)/cofferdams | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Design, fabrication, and installation of temporary gate support shoring | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Estimated Bid Value | $7,500,000.00 | ||||