| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Potable water piping (removal, replacement, and testing) | 300 | feet | $75.00 | $22,500.00 | Construction |
| Related fittings, valves, drain plugs, elbows, pipe supports for potable water | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Backflow preventer (installation and testing) | 1 | each | $2,500.00 | $2,500.00 | Construction |
| Electrical conduit (removal and replacement) for 120V, 240V, 480V service | 600 | feet | $50.00 | $30,000.00 | Construction |
| Electrical cabling/wire (removal and replacement) for 120V, 240V, 480V service | 600 | feet | $75.00 | $45,000.00 | Construction |
| Electrical switches (removal and replacement) | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Electrical junction boxes (removal and replacement) | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Electrical receptacles (removal and replacement) | 1 | lot | $6,000.00 | $6,000.00 | Construction |
| Electrical circuit breakers (removal and replacement) | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Electrical transformers (removal and replacement) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| 600V, 225A circuit breaker (removal) | 1 | each | $500.00 | $500.00 | Construction |
| 600V/400A circuit breaker (replacement and testing) | 1 | each | $3,000.00 | $3,000.00 | Construction |
| Associated cabling for 600V/400A circuit breaker (replacement and testing) | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Light posts (removal, replacement, and reconnection) | 3 | each | $3,500.00 | $10,500.00 | Construction |
| Wooden railing (2x4, 4x4, 6x6) along pier (removal) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Plastic lumber railing along pier (replacement) | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Life ring attached to piping (removal and replacement) | 1 | each | $500.00 | $500.00 | Construction |
| Wooden steps to access floating dock (removal and replacement) | 1 | each | $7,500.00 | $7,500.00 | Construction |
| Project Management, Site Supervision, Mobilization/Demobilization, Permitting, and General Conditions | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||