| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Full Depth Reclamation Method 2, 6-inch depth | 6800 | SQYD | $25.00 | $170,000.00 | Construction |
| Asphalt Concrete Pavement | 1250 | TON | $250.00 | $312,500.00 | Construction |
| Roadway Excavation | 400 | CUYD | $75.00 | $30,000.00 | Construction |
| New aggregate base for parking areas | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Asphalt pavement for new parking areas | 1 | lot | $120,000.00 | $120,000.00 | Construction |
| Concrete ABA compliant curb ramp | 1 | each | $7,500.00 | $7,500.00 | Construction |
| ABA compliant parking spot | 1 | each | $5,000.00 | $5,000.00 | Construction |
| Concrete aprons around existing structures | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Entrance gates | 2 | each | $10,000.00 | $20,000.00 | Construction |
| Culvert replacement | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Super elevation correction | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Traffic control and construction phasing (road closures) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Project Management and General Conditions | 1 | lot | $237,000.00 | $237,000.00 | Professional Services |
| Estimated Bid Value | $1,087,000.00 | ||||