CHANCELLOR PARK SIDEWALK PROJECT, SPOTSYLVANIA, VA (IFB 27-01-SD)

Estimated Value: $400,000
Closing Soon 3 days left VirginiaConstructionifb
Oct 7, 2026
Oct 26, 2026 2:00 PM
Construction
ifb
238310
AI Summary
This bid is for construction services to build approximately 855 feet of 5-foot sidewalk with curb and gutter, enclosed drainage, and an 8-inch waterline along Chancellor Park Drive in Spotsylvania, VA, including additional sidewalk at Willow Pond Drive and a CG-12 installation.
Line Items
ItemQtyUnitEst. Unit PriceEst. TotalCategory
5-foot Sidewalk Construction (along Chancellor Park Drive) 855 linear feet $40.00 $34,200.00 Construction
Curb and Gutter Installation (along Chancellor Park Drive) 855 linear feet $30.00 $25,650.00 Construction
Enclosed Drainage System Installation (along Chancellor Park Drive) 855 linear feet $75.00 $64,125.00 Construction
8-inch Waterline Installation (behind sidewalk) 855 linear feet $120.00 $102,600.00 Construction
Sanitary Service Connections (for waterline) 5 each $2,500.00 $12,500.00 Construction
Sidewalk Construction (at intersection of Willow Pond Drive East and Chancellor Park Drive) 1 lot $25,000.00 $25,000.00 Construction
CG-12 Installation (approximately 965 feet north of Charger Lane) 1 each $15,000.00 $15,000.00 Construction
Site Preparation and Earthwork 1 lot $50,000.00 $50,000.00 Construction
Traffic Control and Management 1 lot $20,000.00 $20,000.00 Construction
Permitting and Inspections 1 lot $10,000.00 $10,000.00 Construction
Project Management and Supervision 1 lot $40,000.00 $40,000.00 Construction
Estimated Bid Value$400,000.00

Want the full details?

Sign up free to see the agency name and the original bid posting link, plus the 1 document, contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.

📎 Purchase_Order_General_Terms___Conditions__PDF_.pdf View
Sign Up Free → Already have an account? Log in

Browse More Bids

Bids in VirginiaConstruction BidsClosing Soon All Bids