| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| 5-foot Sidewalk Construction (along Chancellor Park Drive) | 855 | linear feet | $40.00 | $34,200.00 | Construction |
| Curb and Gutter Installation (along Chancellor Park Drive) | 855 | linear feet | $30.00 | $25,650.00 | Construction |
| Enclosed Drainage System Installation (along Chancellor Park Drive) | 855 | linear feet | $75.00 | $64,125.00 | Construction |
| 8-inch Waterline Installation (behind sidewalk) | 855 | linear feet | $120.00 | $102,600.00 | Construction |
| Sanitary Service Connections (for waterline) | 5 | each | $2,500.00 | $12,500.00 | Construction |
| Sidewalk Construction (at intersection of Willow Pond Drive East and Chancellor Park Drive) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| CG-12 Installation (approximately 965 feet north of Charger Lane) | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Site Preparation and Earthwork | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Traffic Control and Management | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Permitting and Inspections | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Estimated Bid Value | $400,000.00 | ||||