ND NP THRO 204(1) Buck Hill Road

Estimated Value: $7,500,000
Open 12 days left ColoradoConstructionsolicitation
Oct 7, 2026
Nov 3, 2026 9:00 PM
Construction
solicitation
237310
HUBZONE
AI Summary
This bid is for the rehabilitation of approximately 0.75 miles of Buck Hill Road, including addressing a landslide, and reconstructing the Buck Hill Overlook parking lot within Theodore Roosevelt National Park.
Line Items
ItemQtyUnitEst. Unit PriceEst. TotalCategory
Roadway Rehabilitation (pulverization, aggregate, hot asphalt concrete pavement, guardrail, paved ditches, concrete curb and gutter, drainage inlets, culverts, striping, signage) 0.75 mile $4,000,000.00 $3,000,000.00 Construction
Deep Subexcavation for landslide (removal of unsuitable material, replacement with suitable material, geosynthetic reinforcement, subsurface drainage) 1000 linear feet $500.00 $500,000.00 Construction
Buck Hill Overlook Parking Lot Reconstruction (pavement removal, embankment, aggregate base, hot asphalt concrete pavement, accessible parking, concrete sidewalk, curb and gutter, striping, signage, trash receptacles, stone benches) 1 lot $2,000,000.00 $2,000,000.00 Construction
Subexcavation 11000 cubic yards $50.00 $550,000.00 Construction
Geocomposite sheet drain 1000 linear feet $75.00 $75,000.00 Construction
Hot asphalt concrete pavement 2000 tons $150.00 $300,000.00 Construction
Roadway aggregate 5000 tons $50.00 $250,000.00 Construction
24-inch pipe culvert (thick walled HDPE, fused) 550 linear feet $150.00 $82,500.00 Construction
Concrete curb and gutter (tan and onyx colored) 5100 linear feet $70.00 $357,000.00 Construction
Concrete sidewalk (tan colored) 650 square yards $100.00 $65,000.00 Construction
Guardrail 1600 linear feet $80.00 $128,000.00 Construction
New striping and signage (roadway) 1 lot $50,000.00 $50,000.00 Construction
New striping and signage (parking lot) 1 lot $25,000.00 $25,000.00 Construction
Trash receptacles 4 each $1,000.00 $4,000.00 Facilities
Stone benches 4 each $2,000.00 $8,000.00 Facilities
Project Management and Engineering (overall project oversight, coordination, and unforeseen elements) 1 lot $1,000,000.00 $1,000,000.00 Professional Services
Estimated Bid Value$7,500,000.00

Want the full details?

Sign up free to see the agency name and the original bid posting link, plus the 15 documents, contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.

📎 Questions_and_Answers_10_07_2026_ND_NP_THRO_202_1__Buck_Hill_Road.pdf View
📎 6982AF25B000004_IFB_ND_NP_THRO_204_1__Buck_Hill_Road.pdf View
📎 FP-14_Eng.pdf View
+12 more