| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization | 1 | Lump Sum | $5,000.00 | $5,000.00 | Construction |
| Common Excavation | 10 | Cubic Yards | $75.00 | $750.00 | Construction |
| Compaction of Earthwork (Type B) (MR-90) | 10 | Square Yards | $25.00 | $250.00 | Construction |
| Aggregate Base (AB-3) (6” Compacted) | 23.4 | Square Yards | $40.00 | $936.00 | Construction |
| Concrete Footing (Reinforced) (12”) (AE) | 23.4 | Square Yards | $150.00 | $3,510.00 | Construction |
| Precast Concrete Structure (In Place) | 1 | Lump Sum | $1,500.00 | $1,500.00 | Construction |
| Concrete Wall (Reinforced) (9”) (AE) | 4.7 | Cubic Yards | $300.00 | $1,410.00 | Construction |
| Temporary Slope Barrier | 100 | Linear Feet | $10.00 | $1,000.00 | Construction |
| Inlet Sediment Barrier (Set Price) | 1 | Each | $150.00 | $150.00 | Construction |
| Sediment Removal (Set Price) | 1 | Cubic Yards | $99.00 | $99.00 | Construction |
| Estimated Bid Value | $12,605.00 | ||||