| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Asbestos and Lead Paint Removal (from existing restroom structure) | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Removal and Disposal of Existing Artesia Park Restroom Structure | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Site Demolition (excluding restroom structure, e.g., existing pavement, landscaping) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Supply of New Restroom Structure (designed by Romtec) | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Installation of New Romtec Restroom Structure | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Construction of Concrete Pavement (new sidewalks, pads, etc.) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Utility Connections (water, sewer, electrical for new restroom) | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Project Management and General Conditions | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| Estimated Bid Value | $450,000.00 | ||||