| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Construction of Munitions Maintenance and Inspection Facility (KNMD209085) | 1 | lot | $14,000,000.00 | $14,000,000.00 | Construction |
| Micro-pile Foundations for Munitions Maintenance and Inspection Facility | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Cast-in-Place Concrete for Munitions Maintenance and Inspection Facility (slab-on-grade, walls, capping beams, masonry) | 1 | lot | $2,000,000.00 | $2,000,000.00 | Construction |
| Structural Framing and Enclosure for Munitions Maintenance and Inspection Facility (cold-formed metal, insulated metal panels, structural steel) | 1 | lot | $2,500,000.00 | $2,500,000.00 | Construction |
| Standing Seam Metal Roofing for Munitions Maintenance and Inspection Facility (gutters, downspouts, weather barrier) | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Mechanical HVAC Systems for Munitions Maintenance and Inspection Facility (including 20-ton AC systems) | 1 | lot | $1,200,000.00 | $1,200,000.00 | Construction |
| Interior Plumbing for Munitions Maintenance and Inspection Facility | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Lightning/Grounding Protection for Munitions Maintenance and Inspection Facility | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Communication Infrastructure for Munitions Maintenance and Inspection Facility | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Fire Alarm-Mass Notification System for Munitions Maintenance and Inspection Facility | 1 | lot | $600,000.00 | $600,000.00 | Construction |
| Wet-Pipe Sprinkler Suppression System for Munitions Maintenance and Inspection Facility | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| MAC Pad (Material Assembly Center) Concrete Pad (1,167 SY) | 1167 | SY | $150.00 | $175,050.00 | Construction |
| Asphalt Pavement for MAC Pad Access and Egress | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Construction of Conventional Munitions Cube Storage Addition (KNMD209086) | 1 | lot | $14,000,000.00 | $14,000,000.00 | Construction |
| Micro-pile Foundations for Conventional Munitions Cube Storage Addition | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Concrete Wall Structures for Conventional Munitions Cube Storage Addition (12 in. thick, high-hazard) | 1 | lot | $3,000,000.00 | $3,000,000.00 | Construction |
| Cast-in-Place Concrete Slabs for Conventional Munitions Cube Storage Addition | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Structural Steel Framing and Roof Joists for Conventional Munitions Cube Storage Addition | 1 | lot | $2,000,000.00 | $2,000,000.00 | Construction |
| Standing Seam Metal Roofing for Conventional Munitions Cube Storage Addition | 1 | lot | $600,000.00 | $600,000.00 | Construction |
| New Asphalt Pavement for Conventional Munitions Cube Storage Addition Access | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Lightning and Grounding Protection Systems for Conventional Munitions Cube Storage Addition | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Integrated Fire Detection and Alarm Reporting Systems for Conventional Munitions Cube Storage Addition | 1 | lot | $700,000.00 | $700,000.00 | Construction |
| RAB Lighting Exterior Wall Packs (Applicable to both projects) | 1 | lot | $50,000.00 | $50,000.00 | Facilities |
| Estimated Bid Value | $28,000,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 4 documents, contracting-officer contacts and AI response outlines.