| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Road alignment adjustment and subbase enhancement | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Pumphouse replacement and rerouting | 1 | each | $75,000.00 | $75,000.00 | Construction |
| Water service and distribution lines replacement and rerouting | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Point-of-use hydrants replacement and rerouting | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Information board replacement and relocation | 1 | each | $10,000.00 | $10,000.00 | Construction |
| Sewage vault installation for Host Site | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Water service installation for Host Site | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Electric service installation for Host Site | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Sewage vault installation for Volunteer Site | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Water service installation for Volunteer Site | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Electric service installation for Volunteer Site | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Campsite redesign for accessibility, layout, parking, and functionality | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| New stick-built double toilet facility | 1 | each | $100,000.00 | $100,000.00 | Construction |
| New stick-built pump house | 1 | each | $50,000.00 | $50,000.00 | Construction |
| Estimated Bid Value | $1,050,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 5 documents, contracting-officer contacts and AI response outlines.