| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition services (site preparation) | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Precise grading (30 acres) | 30 | acre | $15,000.00 | $450,000.00 | Construction |
| Storm drainage system installation | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| New curb and gutter installation | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Construction of trash enclosures | 10 | each | $15,000.00 | $150,000.00 | Construction |
| Construction of screen walls | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Sidewalks installation | 1 | lot | $600,000.00 | $600,000.00 | Construction |
| Decorative paving installation | 1 | lot | $800,000.00 | $800,000.00 | Construction |
| Asphalt parking lots construction | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| EV chargers installation | 20 | each | $10,000.00 | $200,000.00 | Construction |
| Irrigation system installation (30 acres) | 30 | acre | $12,000.00 | $360,000.00 | Construction |
| Landscaping (planting, soil, mulch, etc. for 30 acres) | 30 | acre | $25,000.00 | $750,000.00 | Construction |
| Site lighting installation | 1 | lot | $900,000.00 | $900,000.00 | Construction |
| Project Management and General Conditions (Class A/B Contractor) | 1 | lot | $8,000,000.00 | $8,000,000.00 | Construction |
| Estimated Bid Value | $15,000,000.00 | ||||