| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition and Removal of Existing Sewage Lift Station Infrastructure | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| New Sewage Lift Station Wet Well Construction | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Submersible Sewage Pumps (Duplex System) | 2 | each | $35,000.00 | $70,000.00 | Construction |
| Pump Control Panel and Electrical System | 1 | each | $60,000.00 | $60,000.00 | Construction |
| Force Main Piping and Valves (Installation) | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Gravity Sewer Piping and Connections (Installation) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Site Work, Excavation, Backfill, and Restoration | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| SCADA/Telemetry System Integration | 1 | each | $40,000.00 | $40,000.00 | Construction |
| Generator and Automatic Transfer Switch (Installation) | 1 | each | $75,000.00 | $75,000.00 | Construction |
| Permitting, Engineering, and Project Management | 1 | lot | $150,000.00 | $150,000.00 | Professional Services |
| Contingency and Unforeseen Conditions | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Testing, Commissioning, and Startup | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Security Fencing and Access Control | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Estimated Bid Value | $1,250,000.00 | ||||