| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Phased demolition of existing 8' diameter CMP culvert | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Demolition of existing road surface and sidewalk | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Bank stabilization and grading | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Dewatering services | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Dredging services | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Roadway grading | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Water main relocation | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Installation of new 24-foot span 3-sided rigid frame bridge structure | 1 | each | $1,500,000.00 | $1,500,000.00 | Construction |
| Installation of new HMA walkway | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Installation of new HMA berm | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Streambed restoration | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Roadway paving | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Other work, appurtenances, and incidental items (project management, engineering oversight, site safety, environmental compliance, etc.) | 1 | lot | $305,000.00 | $305,000.00 | Construction |
| Estimated Bid Value | $2,500,000.00 | ||||