| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Installation of 12" to 48" storm sewer | 4000 | linear feet | $150.00 | $600,000.00 | Construction |
| Installation of 10" to 36" sanitary sewer | 200 | linear feet | $200.00 | $40,000.00 | Construction |
| Installation of 4" to 16" water main | 5100 | linear feet | $100.00 | $510,000.00 | Construction |
| Sanitary sewer lining (6" to 36") | 5500 | linear feet | $75.00 | $412,500.00 | Construction |
| Pavement removal | 6700 | square yards | $25.00 | $167,500.00 | Construction |
| Pavement patching | 25400 | square yards | $50.00 | $1,270,000.00 | Construction |
| Pavement surface milling | 18300 | square yards | $10.00 | $183,000.00 | Construction |
| Curb and gutter removal and replacement | 900 | linear feet | $70.00 | $63,000.00 | Construction |
| Sidewalk removal and replacement | 5200 | square feet | $15.00 | $78,000.00 | Construction |
| Removal and/or abandonment of existing water and sewer mains | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Water and sewer main adjustments | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Water and sanitary service re-establishment | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Parkway restoration and other miscellaneous items of work | 1 | lot | $5,500,000.00 | $5,500,000.00 | Construction |
| Estimated Bid Value | $10,500,000.00 | ||||