| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal and disposal/recycling of existing commercial-grade steel pavilion shelter | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Rehabilitation and refinishing of existing concrete slab | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Furnishing of new commercial-grade steel pavilion shelter (materials) | 1 | each | $40,000.00 | $40,000.00 | Construction |
| Installation of new commercial-grade steel pavilion shelter | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Estimated Bid Value | $75,000.00 | ||||